Fire Department Project Update – April 2021

Demolition: Phase 2 demolition and hazardous waste abatement is ongoing. The Apparatus Bay doors on Main Street were removed and replaced.

Cast-in-Place Concrete: Dumpster pad and Tight Tank Apron were formed and placed.

Masonry: Brick veneer was installed at the addition. Stone veneer installation at the retaining wall is ongoing.

Roofing: Asphalt shingle roof at the addition front entrance is complete. Gutter and roof edge metal work is ongoing.

Carpentry: Cabinets and countertops were installed. Trim work at windows and gables are complete. Shutters were installed.

Specialties: Toilet room accessories, Whiteboards in the Training Room, and Lockers were installed.

Equipment: Appliances were installed, with the exception of the backordered range hood. Television mounts were installed.

Furnishings: Window shades were installed.

Finishes: Interior painting in the Addition is complete. Exterior painting is ongoing. Tile backsplash in kitchen is complete. Carpet tile in the Training Room, Rear Vestibule and Locker Room are complete. Vinyl stair treads were installed.

Doors and Windows: Door hardware installation is ongoing. Installation of overhead doors at the Main Street entrance is ongoing.

Caulking: Caulking for the windows, control joints and exterior doors are complete.

Fire Protection: Sprinkler system was tested and is operational.

Electrical: Ngrid connected the new service. The Generator is operational. Fire Alarm Panel and Radio Control box are operational. Exterior light poles were placed. Communication cabling is temporarily patched into existing equipment. Phase 1 -Access Control system is activated in Addition. Cameras were installed but are not active.

Phase 2 – electrical work has begun.

Plumbing: Finish plumbing is complete in the addition. Plumbing vents are complete in the Apparatus Building. Phase 2 Rough Plumbing is ongoing.

HVAC: The HVAC system is operational. Testing and Balancing is complete. Commissioning process has begun.

Earthwork: The remaining bituminous paving base and berm was placed. The reclaimed asphalt placement is ongoing. Placement of loam around the site is ongoing.

Schedule Assessment: Phase one is complete and temporary CO was issued on 4/12/21.

P&P is approximately two weeks behind based on their preliminary project schedule.

 

Are we on time: Yes. The Project is currently projected to be complete in July of 2021.

Are we on budget: Yes

Next Steps:  Work on Phase 2 is ongoing