Fire Department Project Update – May 2021

Weather: Weather was favorable for construction. No time was lost to unseasonable weather this month. Demolition: Phase 2 Demolition and Hazardous Waste Remediation was completed. Selective Demolition of the administration side and apparatus bay was completed. Cast-in-Place Concrete:

Front apron was constructed. Third party testing confirmed base soil compaction, steel reinforcement, and concrete was in compliance with the specifications. Masonry: Masonry restoration and re-pointing is ongoing.

Stone veneer on retaining wall is ongoing. Patching of CMU walls on the administration side is complete. Metals: Steel Lintels were installed at new masonry door openings. Roofing: Gutter and snow rails were installed.

Insulation: Spray foam insulation was installed in the administration attic.

Carpentry: Interior framing in the administration side complete. A LVL beam was installed in the Deputy’s office to support the attic. Finishes:

Exterior painting is ongoing. Doors and Windows: The Overhead doors at the Main Street entrance have been installed. Windows have been installed on administration side. Steel door frames in the administration side is ongoing. Fire Protection: Phase 2 Sprinkler work is ongoing.

 

Are we on time: Slightly behind. The Project is currently projected to be complete in August 2021 .

Are we on budget: Yes Next Steps: Work on Phase 2 is ongoing.