Fire Department Project Update – June 2021

Masonry: Brickwork restoration, replacement and re-pointing is complete. The stone veneer at the retaining wall is complete. The brick sills at the front of the station were replaced.

Roofing: Gutter and sheet metal work is ongoing. The zinc coated plumbing vent flashings and an exhaust curb were installed. Warranty and close out submittals are under review by S&A.

Insulation: Spray foam and sound insulation batts were installed in the Administration wing.

Carpentry Interior framing in the Administration building is complete.

Finishes: Apparatus Bay walls were painted. Drywall in the Administration wing is 99% complete.

Ceramic tile in the Administration Bath #106 and Janitor’s Closet #109 was installed.

VCT flooring was installed in the Electrical room #108.

Doors and Windows: Steel doors and frames in the Administration wing were installed except for Door 102.

Caulking: Exterior caulking of windows and doors is ongoing.

Fire Protection: Phase 2 Fire Protection rough is complete and pending inspection by BER.

Electrical: Phase 2 Electrical rough and finish is ongoing. A lightning protection system was installed at the Fire Station and the Apparatus Building.

Plumbing: Phase 2 Plumbing rough is complete, pipe insulation and identification labels were installed. Trench Drains were completed in the Apparatus Bay.

HVAC: Phase 2 HVAC work is ongoing. HVAC ductwork is complete and insulated.

Condensate lines were run and insulated.

Site work: The East High St. water services patch was replaced. Rough grade of the front sidewalk was completed. Storm drains and manhole on the north west side of the site were constructed.

Utilities: A sewer back up occurred and was cleared. Video inspection of the sewer pipe determined that a section of pipe had positive pitch. Excavation and reconstruction of the sewer pipe is ongoing.

Landscaping: Maintenance of plantings is ongoing.

Metal Building: Snow guards are in place. Door closers were installed on the personnel doors. A

Certificate of Occupancy was granted for the Apparatus Building.

Schedule Assessment: P&P is approximately 2 weeks behind based on their preliminary project schedule.

 

Are we on time: Slightly behind. The Project is currently projected to be complete in early August 2021.

Are we on budget: Yes

Next Steps:  Work on Phase 2 is ongoing.