Schedule:
Substantial Completion was achieved on August 3, 2021.
Concerns/Issues:
- Ceiling occupancy/vacancy sensors in various areas are not working.
- Attic stairway light not dimming.
- Apparatus Bay lighting goes into emergency mode when shut off.
- Apparatus Bay floors showing tire marks.
- Emergency Supply Room has no conditioned air supply.
- No Uninterrupted Power Supply for HVAC controls.
- Washer Extractor Wiring Issue. Pending CO review from BER.
- Roof Leak
- Landscaping Issues
Are we on time: The Project is substantially complete.
Are we on budget: Yes
Next Steps: Punch List items are being corrected. The committee is planning for a ribbon cutting ceremony for October 2, 2021.