Fire Department Project Update – June 2020

The committee met with the Board of Selectman in June to recommend that P & P General Contractors Inc. be awarded the contract for the Fire Station, which they did award. A kick off meeting was held on June 24th with all subcontractors to review procedures and protocols for the project duration. The project will officially start in July with a scheduled finish date of June 2021

Are we on time: Yes

Are we on budget: Yes.

Next steps:  General Contractor will begin permitting process, once secured demolition will begin.