Per the last meeting, Town Counsel reviewed the bid documents. The Designer Selection Committee had a virtual meeting with the Board of Selectman on April 2nd to review the final plans. Questions were reviewed and it was determined that the Committee could move forward with advertising the project. The committee met virtually in April to discuss the project progress. The project was advertised in the Brockton Enterprise and Central Register. Due to the Social Distancing guidelines, we hosted a “site only” pre bid walkthrough. 8 contractors attended. Filed Sub bids are due on 5/6/20 at 2:00pm, the General Contractor bids are due on 5/14/20 2:00pm. As of today (4/28/20) over 60 bidders have requested the drawings.
Are we on time: No. As reported last month, the bid schedule slipped about a week. The General Contractor bids are expected on 5/14/20.
Are we on budget: Yes.
Next steps: Review the Filed Sub bids on 5/6/20 and General Contractor bids o