What is the current status? The committee brought the completed contract to the Board of Selectman for signature. Once onboarded, ACG began some preliminary work with the Chief and other stake holders on the Design concept. ACG began work on the
Read moreFire Department Project Update – December 2018
What is the current status? We have advertised for the RFQ?RFP for the Owner’s Project Manager for the project. Submissions were due on December 27th @ 2 p.m. A total of 5 companies sent in submissions for the project. Next Steps: Review
Read moreFire Department Project Update – November 2018
The Board of Selectmen Appointed Alex Sinclair to the Designer Selection Committee. The Designer Selection Committee met to discus the Fire Station time table.
Read more