What is the current status: The committee directed Saccoccio & Associates to begin working with the stakeholders for this project to design a functional facility that has what the Fire Department needs while staying in budget. Throughout the fall the Committee and ACG met to discuss progress. In December of 2019 the Committee met with the board of Selectman to review what had been completed so far. The project has moved into Design Development.
Are we on time: Yes
Are we on Budget: Yes
Next Steps: Saccocio & Associates will continue the Design Development of the project. They have a preliminary meeting scheduled with the Planning board in January for feedback.