Fire Department Project Update – February 2020

The committee met with the Design team and ACG to discuss the project. The project is progressing nicely and the plans should be at 100% by March 6th in order to go out for bid. The Town’s independent review of the plans is ongoing and a productive dialog between the reviewer (4 Leaf) and the architect has been beneficial. The site meeting with Planning Board is set for March 5th at 7:30pm.

Are we on time: Yes

Are we on budget: Yes

Next Steps: The Design team will meet with the Planning board for Site Review. The project will go out for bid at the end of March