In August weekly project meetings were held with a committee member present. The Committee met to discuss the progress on the 27th.
Site Work: Trees have been cleared. Excavated rock at the site of the future Apparatus Building and excavated down to good sub grade and proof rolled the sub grade. Sub grade was inspected by Briggs Engineering. Structural Fill was brought in and placed in 8” lifts with compaction tested by ATC. The Apparatus Building foundation has been excavated and footing and walls are in place. The existing Building foundation has been excavated and footing and walls are in place. The existing fill that was disturbed at the site of the former Police Station has been excavated and filled back in. The material was placed in 8” lifts with compaction tested by ATC. Excavation for the footing and foundation of this addition is underway. Abatement of ACM caulking at the Apparatus Overhead doors and demolition of the ACM ceiling in the Electrical Room was completed.
Masonry/Cast in Place Concrete: The CMU wall that was damaged during building demolition has been rebuilt. Footings and walls for the new Apparatus Building have been formed and poured.
Electrical: MAK installed the grounding wire for the new Apparatus Building and the Electrical Inspector inspected and approved the work. Electrical sleeves were installed in the Apparatus Building foundation. Temporary electrical shed was delivered to the jobsite. Electrical panel boxes were delivered.
Plumbing: The new Septic Tank was installed and tied in for use as a Tight Tank until the new septic system is completed. Existing septic tank was pumped and is ready for removal. Plumbing sleeves were installed in the Apparatus foundation.
Demolition and Abatement: Hazardous materials in the former Police Station wing were abated, and the wing was demolished.
Are we on time: No, the project is approximately 2 weeks behind schedule. The Project is currently projected to be complete in July of 2021.
Are we on budget: Yes
Next Steps: Finalizing finishes for all outside and inside materials by the Committee. The Addition foundation work will continue. Under slab plumbing of the apparatus building will begin.