Site and Earthwork Work is ongoing for the Septic System the septic pump chamber was installed and ready for connection. The septic field is nearing completion. Large rocks and unsuitable soils have been removed from the site. Underground piping for storm drains and a manhole were installed. Work has begun on the new water service.
Masonry/Cast in Place Concrete: Concrete Slab for the Apparatus Building and the addition were placed. Masonry materials have been delivered to site and work is expected to begin the first week of November.
Demolition: The rear wall and overhead doors of the existing apparatus bay have been removed.
Carpentry: A temporary support wall was erected in the existing apparatus bay to allow for demolition. Framing of the addition is underway.
Electrical: The underslab conduit and floor boxes for addition have been installed. Conduit has been assembled for the ductbank to the Apparatus Building.
Plumbing Floor drain was installed in the Apparatus Building. Waste and vent piping installed in the addition. Gas piping began for the new gas service.
Special Construction Metal Apparatus Building was delivered; however, the roof trusses were sized incorrectly. New trusses are scheduled to be manufactured and delivered asap.
Schedule: P&P has recovered time and the project is ahead of schedule based on the original baseline schedule.
Concerns/Issues with the Apparatus Building continue to delay that portion of work. Because its completion is not currently in the critical path of other work, it is not
expected to impact the overall project.
Are we on time: Yes! Time was made up on site and we are back on track. The Project is currently projected to be complete in July of 2021.
Are we on budget: Yes
Next Steps: Work continues on the addition at the former Police site as well as the septic system. preparing for the new building behind the station.