Site and Earthwork is ongoing, new water service was completed. The light pole bases are onsite, the septic system was tested and approved except for permanent power.
Masonry/Cast-In-Place Concrete, the concrete slab for the apparatus building extension has been placed and finished. The wall at the apparatus bay extension is near completed. The top of the wall needs to be cut back to the roofline. The walls for the compressor room and the decon is constructed.
Demolition; the relocation of the gas meter allowed for the generator pad to be demolished.
Carpentry; the wood trusses for the new addition were installed and completed. The Southside of the existing apparatus bay roof has been covered with Zip Sheathing. The exterior trim has been installed at the new addition, installation of trim for the existing apparatus bay is ongoing. Interior framing for the new addition, along with metal door frames is ongoing. Windows have been installed at the east and southside of the new addition.
Electrical; the duct bank to the apparatus building is partially installed. Installation of electrical conduits to the addition is ongoing.
Plumbing; trench drain was installed in the Apparatus Bay extension slab. Waste and vent piping were installed in the decon room. A gas leak was traced by Glionna Plumbing and repaired. The new gas meter was installed.
Special Construction; Metal Apparatus is near completion. Overhead doors are due in the middle of December.
Schedule: P & Ps preliminary project schedule indicates doors and windows to be completed on 12/1/20 this portion of the work is 4 days behind schedule, Interior portion in the new addition is 95% complete, this work is 10 days ahead. Overall project is mostly on schedule.
Concerns/Issues; The existing apparatus CMU walls infills were constructed without steel reinforcement and seismic ties required by the current code.
Are we on time: Yes. The Project is currently projected to be complete in July of 2021.
Are we on budget: Yes
Next Steps: Completion of the Metal Apparatus Building and the overhead doors to be installed. Work continues on the new addition