Fire Department Project Update – September 2020

Site Work: R.J Roy, the Site Work Contractor began the excavation for the addition to the Fire Station. Unsuitable materials were discovered at the South, East and North side of the excavation. With the direction of the Geoengineer from Paul B. Adinger & Associates, Inc., unsuitable materials were removed, and the bottom of the footings were approved.

Footings and walls were formed and placed, and backfilling began. Structural fill was imported and placed in 8” lifts and compaction done to 95%, under the supervision of ATC. The location of the piers within the Southside addition were excavated down to approved subgrade, under the supervision of the Geotech, the fill was then placed in 8” lifts with compaction to 95%. Compaction testing was provided by ATC.

The interior perimeter of the Apparatus Building was excavated by P&P in order to install 2” thick rigid insulation. Interior perimeter was then back filled with structural fill then placed in 8” lifts and compacted to 95%. Compaction testing was performed by ATC.

Ngrid removed the guy wire and placed a new Pole on the southeast corner at Main St.

Unit Price rock removal is ongoing.

Masonry/Cast-in-Place Concrete: Footings and walls for the Fire Station addition were formed and placed. Rebar in the walls and footings were inspected by ATC. Concrete cylinders were collected for break test by ATC.

Electrical: The under-slab conduit for new Apparatus Building was installed. The ground wire at the Fire Station addition was installed. Work is underway to relocate the temporary power at the Electrical Shed.

Plumbing: Columbia Gas has been onsite and has discussed the new location for the gas meter. Glionna Plumbing delivered materials and work is underway for underground trench drain.

Schedule: According to P&P’s original project schedule, the Apparatus Building is about four weeks behind schedule. Finished slab was due to be completed on 9/2/20. Slab on Grade placement is now scheduled for 10/2/20. The Apparatus Building is now scheduled for 10/26/20.

The slab at the new addition was due to be completed on 10/1/20.The rough framing at the new addition was scheduled for start on 10/2/20, current schedule unknown.

Concerns/Issues: On September 22, the excavator hit the guy wire for utility pole of the Fire Station at approximately 7:30 AM. E High St was closed off. No one was injured and Ngrid was on scene to cut the lines and make safe. Because of the down lines National Grid is replacing the existing pole on the Northside of E. High St. GC submitted a claim for the relocation of the generator. ACG and S&A believe the work is unnecessary and the problem is the GC is doing work out of sequence. The removal of generator is scheduled to be completed in Phase 2. Section 26 00 00 Electrical also addresses the issue of temporary power, Paragraph 1.27 B “all necessary transformers, meters, cables, panelboard, switches, and accessories are required for temporary light and power.

 

Are we on time: No, the project is approximately 2 weeks behind schedule. The Project is currently projected to be complete in July of 2021.

Are we on budget: Yes

Next Steps: Work continues on the addition at the former Police site as well as preparing for the new building behind the station.