Cast-in-Place Concrete: Concrete landings were placed at the Southside Addition, the Rear Vestibules, and the Apparatus Building. Equipment pads were placed for the AC Condenser, Compressor, and the Water Heater. Masonry: Brick Veneer installation which began this week is ongoing.
Read moreFire Department Project Update – February 2021
In February 2021 the committee brought an article to Special Town Meeting refunding the monies for Fagan Drive costs from the Stabilization account in the amount of $312,683. The article also called for using $700,000 from the Stabilization fund in
Read moreFire Department Project Update – January 2021
Site and Earthwork: The storm water infiltration basin and sediment forebays were cut and filled. The infiltration basin’s overflow was piped to the manhole on Butler Ave and loose laid stone was placed on the embankment at the southeast property
Read moreFire Department Project Update – December 2020
Site and Earthwork: Site Work is ongoing. Structural fill from TL Edwards was tested and approved and used as a base for the asphalt paving. Asphalt base was applied to the driveways. ATC was onsite to test temperature and compaction.
Read moreFire Department Project Update – November 2020
Site and Earthwork is ongoing, new water service was completed. The light pole bases are onsite, the septic system was tested and approved except for permanent power. Masonry/Cast-In-Place Concrete, the concrete slab for the apparatus building extension has been placed
Read moreFire Department Project Update – October 2020
Site and Earthwork Work is ongoing for the Septic System the septic pump chamber was installed and ready for connection. The septic field is nearing completion. Large rocks and unsuitable soils have been removed from the site. Underground piping for
Read moreFire Department Project Update – September 2020
Site Work: R.J Roy, the Site Work Contractor began the excavation for the addition to the Fire Station. Unsuitable materials were discovered at the South, East and North side of the excavation. With the direction of the Geoengineer from Paul
Read moreFire Department Project Update – August 2020
In August weekly project meetings were held with a committee member present. The Committee met to discuss the progress on the 27th. Site Work: Trees have been cleared. Excavated rock at the site of the future Apparatus Building and excavated
Read moreFire Department Project Update – July 2020
he project officially began on July 9th P&P mobilized and began work. Construction trailers, construction fence, and temporary utility have been installed. Site survey was completed. Tree clearing commenced and is on-going. Demolition, cut, cap, and make safe of former
Read moreFire Department Project Update – June 2020
The committee met with the Board of Selectman in June to recommend that P & P General Contractors Inc. be awarded the contract for the Fire Station, which they did award. A kick off meeting was held on June 24th