AVON – Chief Robert Spurr and the Avon Fire Department would like to remind residents to check their smoke and carbon monoxide alarms when setting their clocks ahead for daylight saving time this weekend. Daylight saving time begins at 2 a.m.
Read moreAvon Fire Department Announces Information on 2023 Open Burning Season
AVON – Chief Robert Spurr and the Avon Fire Department would like to remind Avon residents that open burning season begins Jan. 15 and runs through May 1. A permit is required to open burn in compliance with Massachusetts law. To
Read moreAvon Fire Department Shares Holiday Fire Safety Tips For Decorating This Season
AVON – Chief Robert Spurr and the Avon Fire Department would like to share important fire prevention tips for community members to be mindful of while decorating for the holidays. According to the National Fire Protection Association (NFPA), fire departments
Read moreAvon Fire Department Responds to Fatal Crash on Route 24 Early Saturday Morning
Chief Robert Spurr reports that the Avon Fire Department responded to a fatal crash early Saturday morning on Route 24.
Read more*VIDEO* Avon Fire Station Re-Dedication
Click here to watch the Fire Station Re-Dedication
Read moreFire Department Project Update – August/September 2021
Schedule: Substantial Completion was achieved on August 3, 2021. Concerns/Issues: Ceiling occupancy/vacancy sensors in various areas are not working. Attic stairway light not dimming. Apparatus Bay lighting goes into emergency mode when shut off. Apparatus Bay floors showing tire marks.
Read moreFire Department Project Update – July 2021
Demolition: Demolition and abatement work is complete. Concrete: Concrete work is complete. Masonry: The lead flashing at the front entrance roof and the cornice returns were completed. Metals: Miscellaneous Metals work is complete. Caulking :Interior caulking at the apparatus bay
Read moreFire Department Project Update – June 2021
Masonry: Brickwork restoration, replacement and re-pointing is complete. The stone veneer at the retaining wall is complete. The brick sills at the front of the station were replaced. Roofing: Gutter and sheet metal work is ongoing. The zinc coated plumbing
Read moreFire Department Project Update – May 2021
Weather: Weather was favorable for construction. No time was lost to unseasonable weather this month. Demolition: Phase 2 Demolition and Hazardous Waste Remediation was completed. Selective Demolition of the administration side and apparatus bay was completed. Cast-in-Place Concrete: Front apron
Read moreFire Department Project Update – April 2021
Demolition: Phase 2 demolition and hazardous waste abatement is ongoing. The Apparatus Bay doors on Main Street were removed and replaced. Cast-in-Place Concrete: Dumpster pad and Tight Tank Apron were formed and placed. Masonry: Brick veneer was installed at the